Progress Map

Phase 1 Schedule (as of October 6, 2021)

Currently working in

Section 5 Nibinamik to Webequie
  • 48% complete, approximately 86 km of fibre placed
  • Completion projected for November 2021
Section 1 Aroland to Marten Falls
  • Partially complete from Far North Boundary to Marten Falls.
  • The section from Aroland to the Far North Boundary will be completed by November, 2022
Section 2 Marten Falls to Eabametoong:
  • 92% complete, approximately 167 km of fibre placed
  • Final completion scheduled for April, 2022
Section 3 Eabametoong to Neskantaga:
  • 46% complete, approximately 57 km of fibre placed
  • Completion scheduled for Summer of 2022
Section 4 Neskantaga to Webequie:
  • Projected Construction Summer 2022

All PoP shelter placement and set up will continue,

please see below:

Aroland:
  • Pop shelter has been placed, still needs power and to be connected to longhaul network.
Marten Falls:
  • PoP shelter placement pending community provided cost estimate for site prep work of shelter site.
Nibinamik:
  • PoP shelter placement pending community provided cost estimate for site prep work of shelter site.
Eabametoong:
  • PoP shelter placement pending community provided cost estimate for site prep work of shelter site.
Schedule Image
Schedule Image
Schedule Image
Schedule Image