Phase 1 Schedule (as of October 6, 2021)
Currently working in
Section 5 Nibinamik to Webequie
- 48% complete, approximately 86 km of fibre placed
- Completion projected for November 2021
Section 1 Aroland to Marten Falls
- Partially complete from Far North Boundary to Marten Falls.
- The section from Aroland to the Far North Boundary will be completed by November, 2022
Section 2 Marten Falls to Eabametoong:
- 92% complete, approximately 167 km of fibre placed
- Final completion scheduled for April, 2022
Section 3 Eabametoong to Neskantaga:
- 46% complete, approximately 57 km of fibre placed
- Completion scheduled for Summer of 2022
Section 4 Neskantaga to Webequie:
- Projected Construction Summer 2022
All PoP shelter placement and set up will continue,
please see below:
Aroland:
- Pop shelter has been placed, still needs power and to be connected to longhaul network.
Marten Falls:
- PoP shelter placement pending community provided cost estimate for site prep work of shelter site.
Nibinamik:
- PoP shelter placement pending community provided cost estimate for site prep work of shelter site.
Eabametoong:
- PoP shelter placement pending community provided cost estimate for site prep work of shelter site.